Date: 2026-09-22, 10:00–11:00 Asia/Singapore (SGT, UTC+8)
## N1 — Cutover
Dock scheduling cutover to new tool: 6 Oct. Marta approved the cutover, date subject to carrier confirmation.
## N2 — Carrier notice
Priya to draft carrier notice? We did not assign this before the break.
## N3 — Parallel operation
Marta: Agreed — keep the old tracker read-only for two weeks after cutover. Do not delete it.
## N4 — Training
Noah accepted the action to book the internal training room by 29 Sep. Booking not yet done.
## N5 — Access
Noah: I completed the sample account access check at 09:20 today. No carrier accounts checked.
## N6 — Capacity
Should we run an extra evening slot? No decision; carrier demand estimate missing.