# Cedar Arts manager update — draft

Authored expected output · synthetic teaching example, not an agent run. Reporting period: 19–25 October 2026. Source snapshot: 23 October 2026, 11:00 Asia/Singapore; the period is still underway. References point to [the supplied source pack](input.md).

## Summary

The public booking launch is on hold. Dana Ruiz withdrew the 20 October approval at 10:15 on 23 October. There is no current authority to open booking or send invitations; the tracker’s earlier Approved status does not override that withdrawal. [AUTH, A1, T1, W1]

## Progress this period

Kim's invitation draft is In progress in the 08:00 tracker. Leo accepted the consent-wording revision at 10:15. Neither task is reported complete. [T1, W1]

## Coming up next

- Leo: revise the consent wording by 24 October at 12:00. Completion is not confirmed. [W1]
- Keep the public opening and invitation sending on hold pending fresh approval from Dana. The old 26 October date is historical, not an active approved launch commitment. [AUTH, A1, W1]

## Needs attention

The tracker still shows the earlier approval. This draft preserves that source snapshot and explains the withdrawal; it does not claim the tracker was updated or any external action was stopped. [T1, W1; Source boundary]

## Open questions

Has Dana approved revised consent wording and given fresh launch approval? No such decision is recorded. Kim's suggested 27 October opening is only a proposal, with no approved replacement date. [AUTH, W1, P1]