# Friday review, 2026-10-16 14:00-14:25
N-01: Dana: Labels are done from my side. PDF revision C is ready, but Maya has not signed it. Do not print before release.
N-02: Maya: I will review the labels Monday before noon. That is a review commitment, not release today.
N-03: Jules: Friday arrival in the tracker is my requested date. No supplier confirmation. I will call Monday by 10:00.
N-04: Maya: I accept Eli's room map revision B, including reduced storage. W-102 is complete.
N-05: Dana: Tuesday 16:00-18:00 is empty. I can ask Eli. He has not accepted. I will report Monday at 11:00.
N-06: Noor: I need to decide whether to authorize two paid cover hours. I have not approved them. Bring the remaining gap Monday before noon.
N-07: Ravi: Eighteen of twenty-four stock lines matched. Six exceptions are not confirmed missing equipment. I will chase sign-out sheets Monday by 10:30.
N-08: Maya: If the supplier misses Friday, we need a new launch-date choice. I am not approving Tuesday now. Bring an actual slot and any alternative by Monday noon.