# Manager update — Monday 19 October, 11:00
W-101 labels were released by Maya at 09:10; printing may proceed. W-102 room map remains accepted. [M-01; N-04; M-06]
W-103 missed original Friday 16 October delivery. Tuesday 20 October 15:00 is confirmed, but D-04 launch date remains pending Maya's comparison with an expedited alternative. Its price and availability are unknown. No invitations yet. [T-103; M-02; M-05]
Eli accepted Tuesday 16:00-17:00. W-104 has one hour, 17:00-18:00, uncovered. D-03 still needs Noor's paid-cover decision before noon. [M-03; N-06]
W-105 is 20/24 matched with four exceptions, not confirmed losses. No new completion deadline is evidenced. [M-04]
Jules obtains an expedited alternative; Maya decides by noon. Dana takes the remaining staffing gap to Noor. The desk is not launch-ready. [M-03; M-05]